Mixer Retrieval and Replacement
Reason for activity
Customer experiencing loss of mixing and consequent lack of gas production.
How we helped
Birch Solutions were able to rapidly respond to the issue to install parts provided by the customer for their 3,500m digester. Work was coordinated with a neighbouring plant to minimise costs.
Elements of the work included:
- Development of project plan and associated project and safety documentation
- Safe de-commissioning for the digester prior to starting work
- Peel back the roof to expose mixer
- Contract lift of mixers
- Installation of new mixers
- Re-installation of double membrane bio-dome
- Start up and re-commissioning support
- Plant optimisation
- Continued support provided
- Service and maintenance
Location: Herefordshire
Plant Type: Agri Biogas plant
Scale: 500kWe
Date: Summer 2020
Mixer Retrieval and Replacement
Reason for activity
Customer experiencing loss of mixing and consequent lack of gas production.
How we helped
Birch Solutions were able to rapidly respond to the issue to install parts provided by the customer for their 3,500m digester. Work was coordinated with a neighbouring plant to minimise costs.
Elements of the work included:
Development of project plan and associated project and safety documentationSafe de-commissioning for the digester prior to starting workPeel back the roof to expose mixerContract lift of mixersInstallation of new mixersRe-installation of double membrane bio-domeStart up and re-commissioning supportPlant optimisationContinued support providedService and maintenance
Location: Herefordshire
Plant Type: Agri Biogas plant
Scale: 500kWe
Date: Summer 2020